Project Timeline
2020
100% Design Submission to the MSBA (Massachusetts School Building Authority)
2019
SumCo Eco Contracting, Site Preparation for new school project substantially complete
90% Design Submission to the MSBA (Massachusetts School Building Authority)
60% Design Submission to the MSBA (Massachusetts School Building Authority)
Southern Middlesex Industries, Demolition and Abatement of existing Minot Forest School substantially complete
Design Development Submission to the MSBA (Massachusetts School Building Authority)
2018
Schematic Design Complete – Target District & MSBA Board Approval of Final Project Scope & Budget
Ballot Vote to Authorize Debt Exclusion
Town Meeting Vote to Allocate Project Funding
MSBA Board Approval of Project Preferred Schematic Design
2017
Preliminary Design Program in Draft form, including list of Potential Site/Building alternatives and Preliminary Cost assessment
Designer Interviews, at MSBA Offices, 40 Broad Street Boston MA
Three design firms shortlisted and invited to interview
Wareham issues request for Designer Services
PMA Consultants selected as Owner’s Project Manager and Contract Executed to oversee Feasibility Study
Wareham issues request for services for Owner’s Project Managers
Feasibility Study Agreement executed with the MSBA with 71.58% base reimbursement rate
2016